Project Updates
Ahmedabad Metro:
Phase-I Project Progress (as on March’25):
(Operational Length – 40.03km, Operational Stations – 31/32 Stations)
Viaduct – 100%
Civil Work of Stations – 100%
Finishing Work – 99.88%
System Works – 100%
Phase-II Project Progress (as on March’25):
(Operational Length – 20.8km/28.2km, Operational Stations – 8/22 Stations)
Viaduct – 100%
Civil Work of Stations – 84.26%
Finishing Work – 84.26%
System Works – 84.26%
Surat Metro:
Phase-I Project Progress (as on March’25):
(Operational Length – 40.03km, Operational Stations – 31/32 Stations)
Viaduct and Tunneling – 63.98%
Civil Work of Stations – 63.98%
System Works – 63.98%
Depot Work – 63.98%